Sunday, 18 March 2012

Soft Shoe


At the tail end of last week the build passes a significant milestone, but not a normal 'we built something' one. Sparks (Project Manager) declares that there is now too much new and finished wood in the house (the stairs, the upstairs floorboards) that to continue clomping around in rigger boots would be to risk damage to the surfaces. The boys must, instead, wear trainers or, in Dad's case, flat soled desert boots. They buy a rubber mat for the front door to wipe away any grit from their boots when they come in and spend the first 2 hours of Monday having a massive 2-hour 'square away' clearing up tools, picking up offcuts of plaster board and sweeping up dust and rubbish. Sparks even re-arranges his tools and materials stack. It's like a different house.

Deefer

Saturday, 21 January 2012

Taking Deliveries




Thursday should have been a relatively easy day. Had the delivery company taken note of Sparks's warning about narrow lanes, sharp turn into the driveway etc, they might have showed up in sensible lorries. As it was we took delivery of most of the building materials for the project in 2 hits, one on a full size 40 foot artic which assumed we'd have a forklift, the other on a 28 foot Hyab (flatbed lorry with crane), neither of which could make the turn.

This meant that both deliveries were going to be made to the country lane and we'd have to wrangle stuff up to the house. Add to that, some of the stuff was to be the modern composite wall insulation boards, plaster board bonded to thick foam sheets. Plaster board in any form hates to get wet (goes soft, sags and forms bellies in your ceiling which do not go away even if it dries out, as anyone knows who has had a plumbing leak above a ceiling). It was threatening rain and kept delivering heavy squalls which had us racing to cover any exposed stacks before running for shelter ourselves.

Luckily, just along the road from us is one of those magnificent 'Celtic Tiger' big houses which never got occupied (more than one visitor has asked why we didn't buy THAT one!) but which has a hard lay-by out front big enough for a 40 foot artic and a van alongside on the roof-rack of which to tip sheeting from the lorry floor, with still room for cars to pass. But is was another arduous day (not as bad as clay-shovelling, but close!) taking sheets off the lorry 10 at a time and shipping them to the house on the roof rack of Sparks's van.

The 40 footer was emptied by 1pm and we had a 20 minute break before the Hyab arrived, laden with our one ton bags of gravel and sand, the joists, floorboards, door frames, wood for stud walling, bags of cement and plaster, rolls of bitumen sheet for the extension roof, sheets of plywood for same, lead for flashing etc. At least this guy had the crane, so was able to drop piles in and around the entrance or over the hedge. The boys then had to wrangle it up the drive in the van or on the 2CV with trailer in between the showers. Knackered again by about 5pm they left some sheeted till the morning and one of the one ton bags right in the middle of the drive.

This is all a bit physical for Mum so she heads for Dublin to take a belated chance to visit family and friends who we have not been to see since moving over. Questions were starting to be asked! Luckily, Mum's wee Fiat can slip out between the sand bag and the gate post.

Friday is then, of course, filled with squaring away the remaining building materials, left the previous day. It had rained all night but, as seems to be the way of these things, by morning it was clear and sunny and plaster board could be unsheeted and moved at will. We have to move all the stuff from the entrance up to safe places; the timber, the plaster board and the plywood roof sheets for the extension roof. None of it is particularly heavy - plasterboard sheets are 25kgs, so they are mainly awkward and need two men to carry them. They all get carried upstairs one by one and stacked flat. We have now and embarrassment of building materials, meaning the build is turning into a bit of a game of solitaire. We need to move this to get to that, but we can't start that because these are in the way. Sparks is scratching his head trying to plan a sequence of moves and tasks which will work. The wall sheets alone take up the entire living room floor to ceiling.

Tuesday, 3 January 2012

Back to it (and forwards)

Mum and Dad are back in touch with "Sparks" over the weekend. Today we'd been all due back up at Roscommon early hours for Sparks to look at our progress on stripping out ceilings and stud walling and to tell us what was next, but a technical issue has delayed him and he can't now make it. However he does tell us that if we want to start pulling up the living room floor (the only floor we have to get rid of completely, the rest are, all being well, floor board patching jobs) then that would be a good idea. He tells us that we can continue with skirting boards and removing any old wiring or plumbing as this is all being renewed and he also announces (ta daaaa!) that he will be joining us on site all week next week to do the electrical "First Fix".

Electrical installs in houses are done in a series of phases or 'fixes' because it's easier to do some bits before the plasterers or ceiling guys, for example, have done anything, and other bits have to happen after the plasterers or other tradesmen. Sparks will be laying the ring main(s) and any other big grey cables around the house, under floors, above ceilings and between rooms while there is no-one to get in his way. That will be the first bit of construction we have seen so far, after all the destruction, so it will fell good and positive, like we have turned a corner and passed a milestone.

Looking Good